Free Online Quiz on Construction Technology and Management with Certificate

* Attempt the Quiz only once .

* Score will be released only after closing of the quiz .

* If total marks scored is above 40% of the maximum marks , then E- certificate will be emailed immediately . Or in 2minutes

* Only 100 E – certificates will be emailed per day .

K.V.N Mallikharjuna Rao
HOD, Civil Engineering
RISE Krishna Sai Gandhi Group of Institutions, Ongole

Mr. L Venkata Nagaraja
Coordinator, Assistant Professor/CE
RISE Krishna Sai Gandhi Group of Institutions, Ongole

* Link to Apply / attempt the Quiz :

  E QUIZ

       It Consists of 10 Questions. Answer all the Questions

  1. Which of the following significant about an arrow in the network diagram?*

Lenght

Direction

Shape

None of the above

  1. The A-O-N (Activity on Node network system) is preferred over a A-O-A system because*

It allows efficient use of dummy activities

It does not contain activity times

It does not allow dummy activities

It allows revisions and modifications easily

  1. In a PERT analysis, duration of activity is taken as*

Optimistic time

Pessimistic time

Most likely time

Expected mean time

  1. Bar charts are suitable for*

Major projects only

Minor projects only

Medium projects only

Any project

  1. If optimistic time, most likely time and pessimistic time of an activity are 4,5 and 6days respectively, then the expected time of activity will be*

4 days

5 days

9 days

15 days

  1. In a CPM network the activity is non critical if*

EST = LST and EFT = LFT

EST < LST and EFT < LFT

EST > LST and EFT > LFT

EST < LST and EFT > LFT

  1. The independent float affects*

Preceding activities

Succeeding activities

The particular activity involved

All the activities

  1. The direct cost of a project with respect to normal time is*

Minimum

Maximum

Zero

Infinite

  1. The Resource Allocation and Multi-project Scheduling is a techniques of*

PERT

CPM

CPS

Network Analysis

  1. The demand of amount deposited with tender is called*

Tender money

Caution money

Security money

Earnest money